| Client Name | Project Description | Service Description | Start Date | End Date | uration |
|---|---|---|---|---|---|
| Baran Telecom Networks (BTN) of Germany | The work entails the building of Vodacom Mozambique Telecoms infrastructure, RF and Microwave links | 1. Installation - 0.3MW Dish - 1.8Dish 2. Commission & Alignment of MW Link 3. Testing & Documentation 4. Support & Maintenance | September 1, 2010 | October 1, 2011 | 13 Months |
| Reutech (RDL) (PTY) Ltd | Trancomm communications was by Reutech (RDL) to complete a snags list generated from failed sites in Gauteng province. | Work Completed: Azimuth turning, Water proofing, Labelling, Cabinet rewiring, Machenical tilt, Pulling new fibre, DC cabling , 78" fidders, RFO’s, indoor installation and new Greenfields sites. | November 1, 2011 | October 1, 2012 | 12 Months |
| TRF & LAMDA PTY) Ltd | The company completed the commissioning of RF green fields sites 2g, 3G & LTE RF for Telkom8ta in KZN, this included the building of new microwave sites for CellC “ZTE” under Brolaz. Furthermore, the company was involved in the building and commission of the first rollout of 2G&3G Telkom 8ta, in Northwest province | 1. Installation - 0.3MW Dish - 1.8Dish 2. Commission & Alignment of MW Link 3. Testing & Documentation 4. Support & Maintenance 5. Install & Commission of the RAN | November 1, 2012 | December 20, 20`3 | 13 Months |
| CCP PTY PTY) Ltd & Tellco PTY) Ltd | Trancomm Communications was sub-contracted by CCP to build and commission of IP Microwave sites for MTN/ Vodacom. | 1. Installation - 0.3MW Dish - 1.8Dish 2. Commission & Alignment of MW Link 3. Testing & Documentation 4. Support & Maintenance | January 14,2014 | January 31, 2018 | 48 Months |
| MAREDI TECHNOLOGIES PTYPTY) Ltd | Trancomm Communications is currently sub-contracted by Maredi Technologies to build and commission of IP Microwave sites for Vodacom and MTN | 1. Installation - 0.3MW Dish - 1.8Dish 2. Commission & Alignment of MW Link 3. Testing & Documentation 4. Support & Maintenance. MTN Longhauls installation | February, 2018 | To Date | 6 Months |